Semanggi Interchanges Project Has Reached 20 Percent
Reported by Erna Martiyanti | Translated by Nugroho Adibrata
Insha Allah, it will be complete on time
The Semanggi interchanges construction until now has reached 20 percent. It is targeted to be complete in August 2017.
Head of Jakarta Bina Marga Dept, Yusmada Faizal disclosed, foundation construction is completed. And pole has been entered installation project. "The project has reached 20 percent," he stated, at City Hall, Tuesday (9/20).
Semanggi Interchange Project BeginsHe added, it takes over 540 days. It consists of 60 days of planning and 480 days of execution or about 18 months ahead. "Insha Allah, it will be complete on time," he told.
There have been two lanes, namely from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters. It is hoped able to parse traffic jam.
Fund for lane construction amounting to Rp 360 billion is from Japanese company, Mori Company, that is PT Mitra Panca Persada. In details, physical project Rp 345 billion and consultant cost Rp 15 billion. While the contractor is PT Wijaya Karya (Wika).