Pembangunan Simpang Susun Semanggi Capai 20 Persen

Semanggi Interchanges Project Has Reached 20 Percent

Insha Allah, it will be complete on time

The Semanggi interchanges construction until now has reached 20 percent. It is targeted to be complete in August 2017.

Head of Jakarta Bina Marga Dept, Yusmada Faizal disclosed, foundation construction is completed. And pole has been entered installation project. "The project has reached 20 percent," he stated, at City Hall, Tuesday (9/20).

Semanggi Interchange Project Begins

He added, it takes over 540 days. It consists of 60 days of planning and 480 days of execution or about 18 months ahead. "Insha Allah, it will be complete on time," he told.

There have been two lanes, namely from Grogol to Blok M along 796 meters and Polda to Monas along 826 meters. It is hoped able to parse traffic jam.

Fund for lane construction amounting to Rp 360 billion is from Japanese company, Mori Company, that is PT Mitra Panca Persada. In details, physical project Rp 345 billion and consultant cost Rp 15 billion. While the contractor is PT Wijaya Karya (Wika).

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye791 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye698 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye639 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye570 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye446 personDessy Suciati